Prefabricated Structure - Definition,Process & Uses

Topics covered = Introduction of prefabrication construction, need of prefabrication, principle behind prefabrication , material of prefabrication, modular co-ordination , standardization, system, production ,transportation and erection.

Prefabricated Structure - Definition,Process & Uses
Prefabricated Structure - Definition,Process & Uses 

Definition -
Prefabrication is a practice of assembling component of a structure in a factory or other manufacturing site and transporting complete assemblies to the construction site where the structure to be located.

Process of prefabrication -

An example from house building is illustrated the process of prefabrication. The conventional method of building a house is to  transport, brick, timber , cement , sand, steel and construction aggregate etc to the site and to construct house on site.

In prefabricated construction only foundation are constructed in this way while section of the wall, floor and roof are prefabricated at the factory including and window is transported to construction site, lifted to the place by crane.

READ HERE -  Important question for Prefabrication construction and its design technology.

Uses Of Prefabrication - 

  1. the most widely used form of prefabrication in civil engineering is prefabricated concrete and prefabricated steel section, in structure where a particular part is repeated many times.
  2. pouring concrete section in a factory brings line advantages of being able to reuse moulds and the concrete can be mixed on factory  itself no need of transporting,pumping and placing of concrete.
  3. Prefabrication technique are widely used in construction of apartment blocks and housing development with repeated housing units.
  4. Prefabrication of steel section reduces on site cutting and welding costs as well as the associated hazards
  5. this techniques also used in office blocks, where houses and factory building.
  6. Prefabricated steel and glass section are widely used for exterior of large buildings.
  7. Prefabricated bridge elements and system after bridge designer and contractor significant advantages in term of construction time, safety, environment impact, construction ability and cost.
  8. Radio Tower for mobile phone and other services often consist of multiple prefabricated sections.
  9. Prefabrication is widely Used in the assembly of aircraft and spaceship, with component such as wings and fuel tank section often being constructed /manufactured in different countries or state from the final assembly site .
Thus this will insurance about better quality for every contract, helpful for establishing a better durable structure.

Read about Advantages and disadvantages of prefabrication over conventional method in next post 
Friday, June 19, 2015
Posted by Saurabh Gupta

[mvct 202] Prefabrication Design & its Construction Technology

Prefabrication Design & its Construction Technology
 Prefabrication Design & its Construction Technology

Previous year papers for RGPV and other universities having syllabus of Prefabrication Design & its Construction Technology , you can have all paper below,containing prefabricated construction, modular construction, prefabricates, design of prefabricated elements and its construction techniques.

To download complete CTM Notes please join this telegram group https://t.me/+cj3WhHbC86syMTdl 


Note - Repeated question is omitted from some preceding year 

JUNE 2014

  1. Name different mass produced prefabrication of steel reinforced concrete,and masonry one from each in details.
  2. Describe following a) limitation of precast construction in India  b)modular coordination as per NBC of India, c) standardization and its necessity.
  3. Describe plant layout, machine and mould used for precast roofing and wall element .
  4. Describe lift points and  explain design of a member with two and three lift points.
  5. Describe tolerances and derivations and their permissible values for precast components.
  6. Explain design of joints to transfer axial forces moments and shear forces.
  7. Describe following a) V plate system b)lift slab system
  8. Write short notes on following a) Modular Grid b)failure of precast construction c) horizontal transportation equipment d) vertical transportation equipment  e) planning and design module
JUNE 2012 
  1. Explain the necessity and scope of precast construction in India    b) Name Prefab component made by Siporax and their properties.
  2.  a) describe principle of modular construction b) Describe NBO recommendation regarding modular planning
  3. Describe production and erection tolerances and their impact on modular planning.
  4. a) Name precast roofing units. Describe any one with construction and erection procedure.  b)Describe the necessity of standardization in precast construction.
  5. a)Explain design of precast member with three lift points   b) write a short notes on Box prefabricates
  6. Describe an ideal plant layout for the mass production of precast building component.
  7.  a) Describe Vplate sysytem of precast construction  b) name various component for horizontal and vertical transportation
  8. Write short notes on any two of the following
  • failure of precast construction
  • cellular concrete
  • preferred dimension
  • system of prefabrication
JUNE 2010

  1. Write down the advantages and disadvantages of of prefabricated construction.
  2. Write a detailed notes note on use of prefabricated construction in mass housing
  3. what do u understand by tolerance in dimensions in context to prefabricated construction.
  4. What is importance of modular coordination in prefabricated construction. 
  5. Sketch and explain the following component of a prefabricated house- 1) foundation 2) column
  6. Give the detailed classification of prefabricated system.
  7.  What are the requirements for ideal connection in prefabricated construction?
  8. Draw neat sketches of the following joints a) beam to beam b) Beam to coloumn
  9. Describe lift slab technique of prefabricated construction.
  10. Describe glover system
  11. Sketch and explain any two prefabricated roofing elemnts.
  12. Write down the precaution to be taken in erection n assembly of prefabricated construction.
  13. Describe large panel construction.
  14. Write IS code precision for modular planning.
  15. Write short notes on a) Constain's Jack-Block system b) Box Prefabricates
OCTOBER 2009

  1. Describe the properties and use of fly ash in precast construction.
  2. Describe modular grid system and its importance
  3. Name and describe various prefabricates used for the construction of wall.
  4. Describe the plant layout and machineries for the production of prefabricates
  5. Describe the design criteria for lift point.
March 2009
  1. Difference Between a) Fly ash prefabricates and siporex prefabricates   b)cellular concrete and ordinary concrete
  2. What do u mean by industrialized building? discuss necessity and scope .
  3. Define and describe a) basic module b) planning module c) design module
  4. Describe NBC specification for prefabricates
  5. name and describe prefabricates used for roof and foundation construction.
  6. Describe various wall panel and material used.
  7. state and describe various loads to be considered for the design of prefabricates and design considerations.
AUGUST 2008
  1. Define Module. Discuss the Modular planning.
  2. Describe various precast methods, also mention their uses.
  3. Describe with neat sketch the "plant process" for the production of precast concrete element
  4. Name the different "precast clay walling elements" and explain in detail.
FEB 2008
  1. Describe the various prefabricate components of snow cem.
DEC 2011
  1. Write a short note on Silber-Kuhi system.
JULY 2011
  1. Explain in detail any 2 commonly used techniques in prefabricates system.
FEB 2009 (ME Part Time)
  1. How will you account for the stresses during handling of precast element.
  2. What are the transportation system for prefab elements are commonly employed in building site? explain in detail.
  3. Discuss the lift slap construction used  in multistory story building construction.

To download complete CTM Notes please join this telegram group https://t.me/+cj3WhHbC86syMTdl

Tuesday, June 16, 2015
Posted by Saurabh Gupta

Telegram

Notes for M.Tech. CTM (Construction Technology Management) available strictly as per syllabus for all three-semester available. Features: • Notes from Gold Medalist student • Handwritten crisp to the point notes • Printed notes • Video notes of some subjects • Previous year question paper • Solved question paper • Subject/Unit wise arranged • Objective question paper for online exam M.Tech. complete thesis support also available. Join telegram group https://t.me/+cj3WhHbC86syMTdl Complete Mtech Thesis support available: 1) Synopsis 2) Synopsis PPT 3) Thesis 4) Thesis PPT 5) Conference paper These are included in the package Those who only want guidance, msg me for more information https://t.me/+cj3WhHbC86syMTdl
Related Posts Plugin for WordPress, Blogger...

Popular Post

Blogger templates


Copyright @ NotesCivil 2013-2016. Powered by Blogger.

Total Pageviews

- Copyright © CIVIL Engineering STUDY Material , NOTES , Free Ebook